PROJECT AUTHORIZATION | PACKET ID: PMT-670L |
CONTRACT ID | EMARS PROGRAM CODE | AUTHORIZATION NO: | |
1659601D | 16596 | 0 | |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID | PROJECT ID NUMBER | FEDERAL PROJECT NUMBER | 6 YR PLAN ITEM NUMBER | 6 YR PLAN ITEM PARENT NUMBER |
047 006 2 018-021 |
STP 5038130 |
04-80200 | 4-.- |
PROJECT TYPE | PROJECT LENGTH | NUMBER OF BRIDGES | SYSTEMS |
ROADWAY SAFETY-M&P | 0.8090 MI |
PROJECT PHASE & RESPONSIBILITY |
PLANNING | DESIGN | RIGHT OF WAY | UTILITIES |
CONSTRUCTION | TITLE DEEDED TO: | MAINTENANCE | OTHER | |
FUNDING & TIME ACCOUNTABILITY |
PARTICIPATING AGENCIES | |||||||
FEDERAL | STATE | KYTC | LOCAL | OTHER |
ITEM NUMBER | PHASE | FUND | PROGRAM | FEDERAL FISCAL YEAR | STATE FISCAL YEAR |
||
FEDERAL APPR CODE |
CURRENT FUNDING REQUEST | ||||||
4-80200 | D | 1100 | FD04 | 2023 | $2,000,000.00 | ||
CURRENT FUNDING REQUEST TOTAL: $2,000,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE | TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING | $0.00 |
DESIGN | $2,000,000.00 |
UTILITIES | $0.00 |
R/W | $0.00 |
CONSTRUCTION | $0.00 |
NON-HIGHWAYS | $0.00 |
Total: $2,000,000.00 |
REMARKS: | THIS AUTHORIZATION PROVIDES STATE (FD04) DESIGN FUNDS TO BEGIN PRELIMINARY ENGINEERING & ENVIRONMENTAL ACTIVITIES ON THE PROJECT. (FHWA APPROVED DESIGN FUNDING FOR FUTURE FEDERAL MATCH ON OTHER PHASES) |
Project Approval Recommended By: James Ballinger 6/5/2023 |
Signed and Approved by: Jim Gray 6/5/2023 |
AUTHORIZATION LOCATION | ||||||
ITEM NO. | COUNTY | DIST | FACILITY NAME |
ROUTE | LENGTH | SCOPE |
04-80200.00 | HARDIN
|
4 | LEITCHFIELD RD SOUTH MULBERRY | 0.8090 MI | Address safety, mobility, and access management, along with potentially reconfiguring the interchange to I 65. (2022CCN) |